TM 55-607/NAVSEA OP 3221 Rev 2
(d) Sweatboard-to-sweatboard stowage of palletized unit loads of 750-pound bombs in the number 4 deep tank
is shown in figure 9-63. Peculiar to this area is the skin framing that is required to support tier stripping and full-block
structures at the sides of the tank. As in the other stowage areas described previously, the loads are positioned nose-to-
base, and nose boards are used as required. Stowage along the shaft alley requires construction of a nonheat bulkhead
to protect the cargo. This technique is applicable to both sweatboard-to-sweatboard stowage and block stowage.
9-81