NORMAL
MWO effective date is 1 October 1988 and completion date is 1 October 1992.
MWO 5-3805-262-25-1
MODIFICATION
WORK
ORDER
MODIFICATION OF LOADER, SCOOP TYPE, 2 CUBIC YARD,
J . I . CASE CO. MODEL MW24C
Headquarters, Department of the Army, Washington, DC
13
November
1988
REPORTING ERRORS AND RECOMMENDING IMPROVEMENTS
You can help improve this MWO. If you find any mistakes or if you know of a way to improve
these procedures, please let us know. Write a letter or complete and mail a DA Form 2028,
Recommended Changes to Publications and Blank Forms, and mail to: Commander, U.S. Army
Tank-Automotive Command, ATTN: AMSTA-MB, Warren, MI 48397-5000. A reply will be
provided to you.
1. PURPOSE. The purpose of this modification is to install an Alcohol Evaporator Kit on all MW24C
2. PRIORITY. This modification is classified NORMAL.
a. Equipment in use (including equipment in supply or maintenance activity below depot level and
equipment in administrative storage). Equipment in use will be modified as soon as practicable but no
later than the scheduled completion date. Equipment not modified after expiration of Department of the
Army Modification Work Order (DAMWO) scheduled completion date will be reported as NOT MIS-
SION CAPABLE in accordance with applicable Army Regulations.
b. Equipment in wholesale depot supply or maintenance activities. All DAMWO's which have been
incorporated into Depot Maintenance Work Requirement (DMWR), will be accomplished on serviceable
materiel prior to issue and/or subsequent to scheduled completion date. Operational Project Stock stored
at the depots will be modified concurrent] y with Depot Stock. Issue of unmodified materiel is prohibited.
The DAMWO will be applied to unserviceable materiel during the scheduled Depot Maintenance.
c. Prepositioned stock, to include non-prepositioned Materiel Configured to Unit Sets (POMCUS)
operational projects will be applied at once.
Approved for public release; distribution is unlimited.