TM 5-3805-290-23-1
0207 00
1.
For a metal tube to hose installation, install the tube and tighten all bolts finger tight at rigid end.
2.
Install hose and tighten all bolts finger tight.
3.
Put hose in a position where hose does not make contact with machine or other hoses.
427-B0147
4.
Tighten bolts on both connections to proper torque. Follow the prescribed torque sequence for split-flange connections.
Add measurement of gap (A) to measurement of gap (B). Total must not exceed 0.16 in. (4.0 mm).
5.
6.
Move implement control levers to all positions.
7.
Look at hose during movement of implement. Ensure hose is not making contact with machine or other hoses.
N OT E
For hoses that cross an articulation hitch, check for contact during articulation. For hoses that con-
nect to the steering system, check for contact during steering.
8.
9.
If hose contacts other hoses or machine during test, loosen bolts, and reposition hose. Repeat steps 3 thru 8 until there is
no contact.
0207 00-7