TORQUE LIMITS - CONTINUED
0207 00
INSTALLATION OF ADJUSTABLE STOR FITTINGS
This type of fitting is used in many applications. One end of the fitting will be an adjustable STOR fitting. Other end
will be different. Always use same installation procedure for STOR end. Adjustable STOR fittings should be positioned before
tightening.
427-B0148
1.
Put locknut (3), backup washer (4), and O-ring seal (5) as far back on fitting body (2) as possible. Hold these compo-
nents in this position. Turn fitting into mating part. Turn the fitting until backup washer contacts the surface of mating
part.
2.
Put fitting assembly in correct position. Loosen fitting (1) until the correct assembly position is achieved. Do not loosen
the fitting more than 360 degrees. Install tube or hose hand tight to verify the orientation of fitting. Tighten locknut (3)
to torque that is shown on correct chart for fitting.