4
TM 5-3805-291-23-2
TOOLBOX REPLACEMENT
THIS WORK PACKAGE COVERS
Removal, Cleaning and Inspection, Installation
INITIAL SETUP
Personnel Required
Maintenance Level
MOS 62B, Construction Equipment Repairer (2)
Unit
Equipment Conditions
Tools and Special Tools
Upper left front ladder removed from machine (WP
Tool kit, general mechanic's, automotive (Item 90,
Shop equipment, automotive maintenance and
Drawings Required
repair: organizational maintenance, common no.
TM 5-3805-291-23P, Figure 136
Estimated Time to Complete Task
1.0 hr
Lifting equipment, 100-lb capacity
Materials/Parts
Cleaning compound, solvent, type III (Item 7, WP