TILT CYLINDERS REPLACEMENT - CONTINUED
LIFT CYLINDERS REPLACEMENT

Field Maintenance Manual 2 For Loader, Heavy, Scoop: Diesel Engine Driven (Ded), 4-Wheel Drive 4.5 Cubic Yard Rock Bucket And 5.0 Cubic Yard General Purpose Bucket
Page Navigation
  577    578    579    580    581  582  583    584    585    586    587  
img
.
TM 5-3805-291-23-2
TILT CYLINDERS REPLACEMENT - CONTINUED
0152 00
INSTALLATION - CONTINUED
8.
Position new O-ring (5), hose assembly (4), and two
flange halves (3) and install four washers (2) and bolts
(1). Connect hose assembly to tilt cylinder (6).
9.
Install tilt kickout position sensor (WP 0089 00).
10.
Run engine and operate tilt cylinder to verify correct operation of tilt cylinder (TM 5-3805-291-10).
11.
Shut down engine (TM 5-3805-291-10).
12.
Check for leaks.
END OF WORK PACKAGE
0152 00-11/(0152 00-12 Blank)