ARCTIC HEATER INSTALLATION - CONTINUED
BRISTLES REPLACEMENT

Field Maintenance Manual 2 For Loader, Heavy, Scoop: Diesel Engine Driven (Ded), 4-Wheel Drive 4.5 Cubic Yard Rock Bucket And 5.0 Cubic Yard General Purpose Bucket
Page Navigation
  700    701    702    703    704  705  706    707    708    709    710  
img
. . . .
TM 5-3805-291-23-2
ARCTIC HEATER INSTALLATION - CONTINUED
0162 00
INSTALLATION - CONTINUED
66.
Install arctic heater switch (98) in control box (94) with nut (97).
67.
Connect arctic heater switch (98) to cab harness (99).
68.
Install cover (95) on control box (94) with four bolts (96).
69.
Refill fuel tank to correct level (TM 5-3805-291-10).
WAR N I N G
Before operating the machine, secure the steering frame lock in the stowed position. DO NOT operate
machine with steering frame lock connected. Failure to lock steering frame lock into the stowed position
before operating can result in loss of steering and injury or death to personnel.
70.
Install batteries in battery box (WP 0095 00).
71.
Install cables in battery box (WP 0097 00).
72.
Install left side fender on machine (WP 0133 00).
73.
Install left side ladders on machine (Install new arctic kit ladder on fender and battery box) (WP 0129 00).
74.
Fill coolant to proper level (WP 0041 00).
75.
Run engine and verify correct operation of heater system (TM 5-3805-291-10).
76.
Check for leaks.
END OF WORK PACKAGE