BATTERY CABLES REPLACEMENT - CONTINUED
BATTERY CABLES REPLACEMENT - CONTINUED

Field Maintenance Manual 2 For Loader, Heavy, Scoop: Diesel Engine Driven (Ded), 4-Wheel Drive 4.5 Cubic Yard Rock Bucket And 5.0 Cubic Yard General Purpose Bucket
Page Navigation
  215    216    217    218    219  220  221    222    223    224    225  
img
TM 5-3805-291-23-2
BATTERY CABLES REPLACEMENT - CONTINUED
0097 00
INSTALLATION - CONTINUED
13.
Position cable (29) on machine.
14.
Install cable (29), washer (36), and nut (35) on alternator terminal (37).
15.
Install protective cover (33) on cable terminal (34).
16.
Install two clips (17), washers (32), and bolts (31) on cable (29).
17.
Install three clips (17) on cable (29).
18.
Install cable (29), washer (28), and nut (27) on junction (30).
19.
Install protective cover (25) on cable terminal (26).