Refrigerant capacity is 5.5 lb (2.4 kg).
Ensure both valves on manifold gage set are closed.
Ensure the red and blue valves on the recovery station lines are fully closed prior to installing on
machine AC system. Connections will feel loose when valves are open.
Record amount of refrigerant recovered from system.
1.
Install manifold gage set (1) by connecting low pressure hose (2) to suction port (3) of AC compressor (4), and high
pressure hose (5) to discharge port (6) of AC compressor.
2.
Attach charging hose (7) of manifold gage set (1) to inlet (8) on recovery station (9).
3.
Open both valves on refrigerant tank (10).