TM 5-3805-298-23-2
0209
WASTEGATE SOLENOID INSTALLATION
000209
1. Install wastegate solenoid (Figure 9, Item 4) and two bolts (Figure 9, Item 1) on machine.
2. Install two tube nuts (Figure 9, Items 2 and 3) on wastegate solenoid (Figure 9, Item 4).
Figure 9. Wastegate Solenoid.
0209
NOTE
Install wiring harness and wastegate solenoid wiring harness connector as noted during
removal.
3. Install wastegate solenoid wiring harness (Figure 10, Item 2) on clips (Figure 10, Item 1).
Figure 10. Wastegate Wiring Harness and Clips.