TM 5-3805-298-23-4
0416
INSTALLATION
000416
1. Install P-clamp (Figure 1, Item 6), two clamps (Figure 1, Item 12), air conditioning dryer (Figure 1, Item 1),
washer (Figure 1, Item 11), and bolt (Figure 1, Item 10) on bracket (Figure 1, Item 2).
NOTE
Remove caps and plugs as air conditioning lines are installed.
Install air conditioning lines as noted during removal.
2. Install new O-ring (Figure 1, Item 7) on air conditioning line (Figure 1, Item 9).
3. Install air conditioning line (Figure 1, Item 9) and tube nut (Figure 1, Item 8) on air conditioning dryer
(Figure 1, Item 1).
4. Install new O-ring (Figure 1, Item 5) on air conditioning line (Figure 1, Item 3).
5. Install air conditioning line (Figure 1, Item 3) and tube nut (Figure 1, Item 4) on air conditioning dryer
(Figure 1, Item 1).
END OF TASK
FOLLOW-ON TASKS
000416
1. Install left engine access panel (WP 0350).
3. Verify operation of machine (TM 5-3805-298-10).
END OF TASK
END OF WORK PACKAGE
0416-3/(4 blank)