POWER TRAIN
TM 5-3805-258-24-2
DISASSEMBLY AND ASSEMBLY
ASSEMBLE TRANSMISSION
3150-16
TRANSMISSION
Tools Needed
A B C
D E
F G H J K
1P1863 Pliers
1
5P9736 Link Bracket
3
FT833 Clamp
2
1P510 Driver Group
1
1P1684 Pliers
1
6V2156 Link Bracket
2
FT947 Clamp
2
5P4758 Pliers
1
1P520 Driver Group
1
FT834 Clutch Testing
Nozzle
1
NOTE: Inspect all parts for wear or damage and
make replacements if needed. Put clean power train
oil on the parts at assembly.
1. Install two dowels (2) in each side of No. 1
clutch housing (1). The dowels must be in-
stalled 10.5 ± .5 mm (.41 ± .020 in.)above the
outside surface.
2. Heat bearing (3) to a maximum temperature of
135° C (275° F) and install it on shaft (4) as
shown.
3. Install seals (5) and (6) on the shaft.
4. Carefully install shaft (4) in the No. 1 clutch
housing.
CAUTION
Make sure the seals are not damaged when the
shaft is installed in the bore of the No. 1 clutch
housing.
5-279