5-9. BATTERIES AND CABLES MAINTENANCE (CONT)
b. Slave Receptacle.
This task covers removal, cleaning, inspection, and
i n s t a l l a t i o n o f s l a v e r e c e p t a c l e.
TOOLS: No. 1 Common Organizational Maintenance Tool Kit
Combination box and open end wrench set
Screwdriver
Socket wrench set, 3/8 inch drive
Multimeter
MATERIALS/PARTS: Clean cloths (Appendix C, item 1)
Cleaning solvent P-D-680 (Appendix C, item 2)
Detergent (Appendix C, item 3)
Insulation tape (Appendix C, item 5)
Isopropyl alcohol (Appendix C, item 15)
Electrical cleaner (Appendix C, item 19)
Electrical sealer (Appendix C, item 20)
PERSONNEL REQUIRED: Two Construction Equipment Mechanics MOS 62B
NOTE
PRELIMINARY PROCEDURE: Battery ground cable disconnected (page 5-148).
REMOVAL (SHEET 1 OF 2)
(1)
Inside battery compartment, behind left stop light, loosen and remove two
capscrews (1) and lock washers (2).
(2) Tag and disconnect cables (3 and 4).
5-154