18
TM 5-3805-290-10
CONFIGURE MACHINE FOR TRANSPORT
THIS WORK PACKAGE COVERS
Introduction; Tools and Equipment; ROPS/FOPS Removal; Exhaust Stack Removal; Counterweight Removal, Installa-
tion; ROPS/FOPS Installation; Exhaust Stack Installation
INITIAL SETUP
Personnel Required
Tools and Special Tools
MOS 21E, Heavy Construction Equipment Opera-
Notify Unit Maintenance to bring general
tor
mechanic's tool kit, common no. 1 shop equip-
MOS 62B, Construction Equipment Repairer (2)
ment, field maintenance shop equipment, torque
wrench (P/N 162-8718), and nylon strap (400-lb
capacity)
References
Lifting equipment, 1,650-lb capacity
Materials/Parts
Cleaning compound, windshield (Item 3, WP 0031
Materials/Parts - Continued
INTRODUCTION
1.
This work package describes how to configure the machine for transport on highway (WP 0022 00), OCONUS (GIC)
after transport.
N OT E
These procedures are included in this manual as a reference. This does not authorize performance by
the operator.
2.
Assistance from two Unit Maintenance mechanics is required to configure the machine for transport.