TM 5-3805-290-23-2
SECONDARY STEERING RELIEF VALVE REPLACEMENT - CONTINUED
0104 00
INSTALLATION
N OT E
Apply a thin coat of clean oil to all O-rings prior to installation.
1.
Install two new O-rings (15), T (3), and adapter (14) on secondary steering relief valve (4).
2.
Install new O-ring (13) on adapter (9).
3.
Install secondary steering relief valve (4) on left-side of transmission (1) with washer (12) and bolt (11).
4.
Install new O-ring (10) and connect hose (8) to adapter (9).
5.
Install new O-ring (7) and connect hose (6) to T (3).
6.
Install new O-ring (5) and connect hose (2) to T (3).
7.
8.
Operate machine to check for leaks and verify correct operation (TM 5-3805-290-10).
WAR N I N G
Before operating equipment, secure the steering frame lock in the stowed position. DO NOT operate
machine with steering frame lock connected. Failure to lock steering frame lock into the stowed position
before operating can result in loss of steering and injury or death to personnel.
9.
Secure steering frame lock in stowed position (TM 5-3805-290-10).
END OF WORK PACKAGE
0104 00-3/(0104 00-4 Blank)