FUSE, RELAY, CIRCUIT BREAKER, AND ARC SUPPRESSOR REPLACEMENT - CONTINUED
PANEL BOX CIRCUIT BREAKER INSTALLATION

Field Maintenance Manual 2 For Loader, Heavy, Scoop: Diesel Engine Driven (Ded), 4-Wheel Drive 4.5 Cubic Yard Rock Bucket And 5.0 Cubic Yard General Purpose Bucket
Page Navigation
  36    37    38    39    40  41  42    43    44    45    46  
img
TM 5-3805-291-23-2
FUSE, RELAY, CIRCUIT BREAKER, AND ARC SUPPRESSOR REPLACEMENT - CONTINUED
0053 00
CAB CIRCUIT BREAKER REMOVAL
0053 00
1.
Remove two nuts (13) and bolts (14) from circuit
breaker (15).
2.
Remove circuit breaker (15) from bracket (16).
3.
Remove two screws (17) and disconnect two wiring
harnesses (18) from circuit breaker (15).
427-C1334
CAB CIRCUIT BREAKER INSTALLATION
1.
Connect two wiring harnesses (18) and install two screws (17) on circuit breaker (15).
2.
Position circuit breaker (15) on bracket (16).
3.
Install two bolts (14) and nuts (13) on circuit breaker (15).
0053 00
PANEL BOX CIRCUIT BREAKER REMOVAL
N OT E
This procedure shows one circuit replacement in the panel box. Replacement is the same for each circuit in
the panel box.
1.
Remove nut (19) from circuit breaker (20).
2.
Loosen nut (21) and remove one end of buss bar (22)
from circuit breaker (20).
3.
Remove nut (23), washer (24), and wiring harness
(25) from circuit breaker (20).
4.
Remove two screws (26) from circuit breaker (20).
5.
Remove circuit breaker (20) from machine.
427-C1332
0053 00-7