SERVICE BRAKE CONTROL VALVE REPLACEMENT - CONTINUED
SERVICE BRAKE LINES AND HOSES REPLACEMENT

Field Maintenance Manual 2 For Loader, Heavy, Scoop: Diesel Engine Driven (Ded), 4-Wheel Drive 4.5 Cubic Yard Rock Bucket And 5.0 Cubic Yard General Purpose Bucket
Page Navigation
  293    294    295    296    297  298  299    300    301    302    303  
img
. .
TM 5-3805-291-23-2
SERVICE BRAKE CONTROL VALVE REPLACEMENT - CONTINUED
0116 00
CLEANING AND INSPECTION - CONTINUED
3.
Inspect all parts for wear, pitting, cracks, or corrosion and replace if necessary.
INSTALLATION
1.
Install five new O-rings (7) in fitting assemblies (3).
2.
Install five fitting assemblies (3) on control valve (6).
3.
Install control valve (6), two washers (5), and nuts (4) on machine.
4.
Install five new O-rings (2) in fitting assemblies (3) and connect hose assemblies (1) to fitting assemblies.
5.
Fill hydraulic tank (WP 0148 00).
6.
Install front guard (WP 0133 00).
7.
Run engine until normal operating temperature is reached (TM 5-3805-291-10).
8.
Apply pressure to brake pedal several times.
9.
Shut down engine (TM 5-3805-291-10).
10.
Check for leaks around control valve.
11.
Adjust hydraulic tank oil level as necessary (TM 5-3805-291-10).
END OF WORK PACKAGE