TM 5-3805-291-23-2
RIDE CONTROL ACCUMULATOR MAINTENANCE
THIS WORK PACKAGE COVERS
Removal, Cleaning and Inspection, Installation, Discharging/Charging, Testing Ride Control Diverter Valve
INITIAL SETUP
Materials/Parts - Continued
Maintenance Level
Unit
Tools and Special Tools
O-ring (2)
Tool kit, general mechanic's, automotive (Item 90,
Personnel Required
Shop equipment, automotive maintenance and
MOS 62B, Construction Equipment Repairer (2)
repair: organizational maintenance, common no.
Equipment Conditions
Machine parked on level ground (TM 5-3805-291-
10)
Work tool lowered to ground (TM 5-3805-291-10)
Lifting equipment, 150-lb capacity
Parking brake engaged (TM 5-3805-291-10)
Wheels chocked
Materials/Parts
Battery disconnect switch in OFF position (TM 5-
3805-291-10)
Cleaning compound, solvent, type III (Item 7, WP
Steering frame lock connected (TM 5-3805-291-
10)
Nitrogen technical dry cylinder (Item 25, WP 0233
Hydraulic system pressure relieved (TM 5-3805-
00)
291-10)
Oil, lubricating, OE/HDO-5/40 (Item 27, WP 0233
00)
Drawings Required
Oil, lubricating, OE/HDO-15/40 (Item 28, WP
TM 5-3805-291-23P, Figure 152
Estimated Time to Complete Task
Oil, lubricating, OEA-30, Arctic (Item 29, WP
3.0 hr