8
TM 5-3805-290-23-2
DRIVE SHAFT MAINTENANCE
THIS WORK PACKAGE COVERS
Rear Drive Shaft: Removal, Cleaning and Inspection,
Rear U-Joints: Removal, Installation
Installation
Center U-Joints: Removal, Installation
Center Drive Shaft: Removal, Cleaning and Inspection,
Front U-Joint: Removal, Installation
Installation
Carrier Bearing: Removal, Installation
Front Drive Shaft: Removal, Cleaning and Inspection,
Installation
INITIAL SETUP
Maintenance Level
Equipment Conditions
Machine parked on level ground (TM 5-3805-290-
Unit
10)
Work tool lowered to ground (TM 5-3805-290-10)
Tools and Special Tools
Parking brake engaged (TM 5-3805-290-10)
Wheels chocked
Shop equipment, common no. 1 (Item 77, WP 0205
Battery disconnect switch in OFF position (TM 5-
3805-290-10)
Steering frame lock connected (TM 5-3805-290-
10)
Materials/Parts
Drawings Required
Cleaning compound, solvent, type III (Item 9, WP
TM 5-3805-290-23P, Figure 76
Estimated Time to Complete Task
0.5 hr (drive shaft)
Personnel Required
2.0 hr (U-joints) per shaft
1.0 hr carrier bearing
MOS 62B, Construction Equipment Repairer (2)