IMPLEMENT PUMP HOSES, LINES, AND FITTINGS REPLACEMENT - CONTINUED
IMPLEMENT PUMP HOSES, LINES, AND FITTINGS REPLACEMENT - CONTINUED

Manual 2 Loader, Light, Scoop: 2.5 Cubic Yard Multipurpose (Mp) Clamshell Bucket, Diesel Engine Driven (Ded), 4-Wheel Drive Model 924G
Page Navigation
  645    646    647    648    649  650  651    652    653    654    655  
img
. . . . .
TM 5-3805-290-23-2
IMPLEMENT PUMP HOSES, LINES, AND FITTINGS REPLACEMENT - CONTINUED
0135 00
INSTALLATION
1.
Connect hose (22) to combination valve (WP 0124 00).
N OT E
Apply a thin coat of clean oil to all O-rings before installation.
2.
Install new O-ring (25) and fitting (23) on implement pump (5).
3.
Install new O-ring (24) and connect hose (22) to fitting (23).
4.
Connect hose (20) to main control valve (WP 0134 00).
5.
Install new O-ring (21) and position hose (20) on implement pump (5) and install two flange halves (19), four washers
(18), and bolts (17).
6.
Install new O-ring (16) and fitting (15) on implement pump (5).
7.
Install new O-ring (13) and connect hose (12) to fitting (15).
8.
Install new O-ring (14) and fitting (10) on implement pump (5).
9.
Install new O-ring (13) and connect hose (12) to fitting (10).
10.
Install fitting and connect hose (9) to hydraulic tank (WP 0140 00).
11.
Install new O-ring (11) and connect hose (9) to fitting (10).
12.
Install fitting and connect hose (8) to hydraulic tank (WP 0140 00).
13.
Connect hose (8) to implement pump (5) and tighten two clamps (7).
14.
Install fitting and connect hose (4) to hydraulic tank (WP 0140 00).
15.
Install new O-ring (6) and position hose (4) on implement pump (5) and install two flange halves (3), four washers (2),
and bolts (1).
0135 00-4