TM 5-3805-290-23-2
IMPLEMENT PUMP HOSES, LINES, AND FITTINGS REPLACEMENT - CONTINUED
0135 00
C AU T I O N
Wipe area clean around all connections to be opened during removal. Cap lines and hoses and plug open-
ings after removing lines. Contamination of system could result in premature failure.
N OT E
Tag hoses prior to removal to ensure correct installation.
Use a container to catch any fluid that may drain from hoses or system. Dispose of fluid IAW local policy and
ordinances. Ensure all spills are cleaned up.
REMOVAL
1.
Remove four bolts (1), washers (2), and two flange halves (3) from hose (4). Disconnect hose from implement pump (5).
2.
Remove and discard O-ring (6).
3.
Disconnect hose (4) and fitting from hydraulic tank (WP 0140 00) and remove hose from machine.
4.
Loosen two clamps (7) and disconnect hose (8) from implement pump (5).
5.
Disconnect hose (8) from hydraulic tank (WP 0140 00) and remove hose from machine.
6.
Disconnect hose (9) from fitting (10).
7.
Remove and discard O-ring (11).
8.
Disconnect hose (9) and fitting from hydraulic tank (WP 0140 00) and remove hose from machine.
9.
Disconnect hose (12) from fitting (10).
10.
Remove and discard O-ring (13).
11.
Remove fitting (10) from implement pump (5).
12.
Remove and discard O-ring (14).
13.
Disconnect hose (12) from fitting (15) and remove hose from machine.
14.
Remove and discard O-ring (13).
15.
Remove fitting (15) from implement pump (5).
16.
Remove and discard O-ring (16).
17.
Remove four bolts (17), washers (18), and two flange halves (19) from hose (20).
18.
Remove and discard O-ring (21).
19.
20.
Disconnect hose (22) from fitting (23).
21.
Remove and discard O-ring (24).
22.
Remove fitting (23) from implement pump (5).
23.
Remove and discard O-ring (25).
24.
Disconnect hose (22) from combination valve (WP 0124 00) and remove hose from machine.