BATTERIES REPLACEMENT - CONTINUED
BATTERY CABLES REPLACEMENT

Field Maintenance Manual 2 For Loader, Heavy, Scoop: Diesel Engine Driven (Ded), 4-Wheel Drive 4.5 Cubic Yard Rock Bucket And 5.0 Cubic Yard General Purpose Bucket
Page Navigation
  205    206    207    208    209  210  211    212    213    214    215  
img
.
TM 5-3805-291-23-2
BATTERIES REPLACEMENT - CONTINUED
0096 00
INSTALLATION - CONTINUED
13.
Connect cable clamp (13) on cable (10) to battery (14) and tighten nut (12).
14.
Install cover (11) over cable clamp (13).
15.
Position cable (7) on machine.
16.
Connect two cable clamps (16) to batteries (14 and 17) and tighten nuts (12).
17.
Install covers (3 and 9) on cable clamps (16).
18.
Install ladder (WP 0134 00).
19.
Connect cable clamp (19) on cable (2) to battery (17) and tighten nut (18).
20.
Install cover (1) on cable clamp (19).
21.
Close battery compartment door (TM 5-3805-291-10).
22.
Start engine to verify correct operation of electrical system (TM 5-3805-291-10).
23.
Shut down engine (TM 5-3805-291-10).
END OF WORK PACKAGE