TM 5-3805-298-23-4
0398
LEFT BATTERIES INSTALLATION CONTINUED
6. Install positive battery cable (Figure 10, Item 8), three cable clamps (Figure 10, Item 6), bolts
(Figure 10, Item 4) and nuts (Figure 10, Item 5) on three batteries (Figure 7, Item 7).
7. Install positive battery cable (Figure 10, Item 8), washer (Figure 10, Item 3), and nut (Figure 10, Item 2) on
cable clamp (Figure 10, Item 6).
8. Position three boots (Figure 10, Item 1) on three cable clamps (Figure 10, Item 6).
Figure 10. Left Positive Battery Cable.
0398
9. Install plate (Figure 11, Item 3), four washers (Figure 11, Item 2), and bolts (Figure 11, Item 1) on battery box
(Figure 11, Item 4).
Figure 11. Left Battery Box Plate.
0398