TM 5-3805-298-23-4
0400
CLEANING AND INSPECTION
000400
Clean and inspect all parts IAW Electrical General Maintenance Instructions (WP 0174).
END OF TASK
INSTALLATION
000400
NOTE
Route cables and install electrical connections as noted during removal.
1. Position arctic heater wiring harness (Figure 2, Item 3) on machine.
2. Install new tiedown strap (Figure 2, Item 2) on arctic heater wiring harness (Figure 2, Item 3).
3. Connect arctic heater wiring harness connector (Figure 2, Item 1) on lower cab wiring harness connector
(Figure 2, Item 4).
4. Connect arctic heater wiring harness (Figure 3, Item 3) on arctic heater (Figure 3, Item 1).
5. Install new tiedown strap (Figure 3, Item 2) on arctic heater wiring harness (Figure 3, Item 3).
Figure 3. Arctic Heater Wiring Harness.
0400
END OF TASK
FOLLOW-ON TASKS
000400
1. Install right ladder and right lower cab access panels (WP 0347).
2. Verify correct operation of machine (TM 5-3805-298-10).
END OF TASK
END OF WORK PACKAGE