TM 5-2420-231-23-2
0195
REMOVAL CONTINUED
3. Remove two bolts (Figure 2, Item 1) and washers (Figure 2, Item 2) from equalizer cover (Figure 2, Item 3).
4. Remove bolt (Figure 2, Item 5), washer (Figure 2, Item 4), and equalizer cover (Figure 2, Item 3) from machine.
Figure 2. Equalizer Cover.
0195
5. Position rubber boot (Figure 3, Item 4) aside.
6. Remove three nuts (Figure 3, Item 3) and lockwashers (Figure 3, Item 2) from equalizer (Figure 3, Item 1).
NOTE
Tag and mark wires to aid in installation.
7. Disconnect ground cable (Figure 3, Item 8), two 12-V cables (Figure 3, Items 6 and 7), and 24-V cable
(Figure 3, Item 5) from equalizer (Figure 3, Item 1).
8. Remove six nuts (Figure 3, Item 10), bolts (Figure 3, Item 9), and equalizer (Figure 3, Item 1) from machine.