TM 5-2420-231-23-3
0242
INSTALLATION
0242
NOTE
Install lines as tagged and marked during removal.
Remove plugs and caps from hoses and fittings.
1. Connect hydraulic hose (Figure 1, Item 7) to tube (Figure 1, Item 1).
2. Position hydraulic hose (Figure 1, Item 7) and tube (Figure 1, Item 1) on machine.
3. Connect hydraulic hose (Figure 1, Item 7) to tube (Figure 1, Item 8).
4. Position hydraulic hose (Figure 1, Item 3) on machine.
5. Connect hydraulic hose (Figure 1, Item 3) to tube (Figure 1, Item 9).
6. Install resilient mount (Figure 1, Item 4) and clamp (Figure 1, Item 6) on boom cylinder (Figure 1, Item 2).
7. Connect hydraulic hose (Figure 1, Item 5) to boom cylinder (Figure 1, Item 2).
8. Connect tube (Figure 1, Item 1) to boom cylinder (Figure 1, Item 2).
9. Install cap on hydraulic tank (TM 5-2420-231-10).
END OF TASK
FOLLOW-ON TASKS
0242
Check hydraulic oil level and fill as necessary (TM 5-2420-231-10).
END OF TASK
END OF WORK PACKAGE
0242-3/(4 blank)