Nitrogen Charging Procedure - Continued
Nitrogen Charging Procedure - Continued

Manual 2 Loader, Light, Scoop: 2.5 Cubic Yard Multipurpose (Mp) Clamshell Bucket, Diesel Engine Driven (Ded), 4-Wheel Drive Model 924G
Page Navigation
  578    579    580    581    582  583  584    585    586    587    588  
img
TM 5-3805-290-23-2
RIDE CONTROL ACCUMULATOR MAINTENANCE - CONTINUED
0127 00
TESTING AND CHARGING - CONTINUED
Nitrogen Charging Procedure - Continued
N OT E
If nitrogen pressure appears on pressure gage in less time, close pressure regulating screw on regulator
assembly and disconnect hose assembly at coupling assembly next to pressure gage. Close needle valve and
remove coupling assembly. Repeat steps 8 thru 28.
29.
Turn handle (16) on nitrogen charging chuck (15)
fully counterclockwise.
30.
Close regulator assembly (22) and needle valve (18).
31.
Slowly disconnect hose (14) from needle valve (18).
32.
Open needle valve (18).
33.
Remove nitrogen charging chuck (15) from nitrogen
charging valve (12) on accumulator (2).
427-B1029-2
34.
Install protective cap (13) on nitrogen charging valve
(12).
35.
Install guard (11) on accumulator (2) with two bolts
(10).
427-B1028-1
0127 00-10