MAIN HYDRAULIC CONTROL VALVE INSTALLATION - CONTINUED
MAIN HYDRAULIC CONTROL VALVE INSTALLATION - CONTINUED

Field Maintenance Manual 2 For Loader, Heavy, Scoop: Diesel Engine Driven (Ded), 4-Wheel Drive 4.5 Cubic Yard Rock Bucket And 5.0 Cubic Yard General Purpose Bucket
Page Navigation
  1146    1147    1148    1149    1150  1151  1152    1153    1154    1155    1156  
img
TM 5-3805-291-23-2
MAIN HYDRAULIC CONTROL VALVE REPLACEMENT - CONTINUED
0218 00
MAIN HYDRAULIC CONTROL VALVE INSTALLATION - CONTINUED
5.
Connect 12 connectors (35) to main hydraulic control valve (20).
6.
Install two new O-rings (34) in hose assemblies (33)
and connect hose assemblies to main hydraulic control
valve (20).
7.
Install four flange halves (32), eight washers (31), and
bolts (30) on main hydraulic control valve (20).
8.
Install two new O-rings (29) in hose assemblies (28)
and connect hose assemblies to main hydraulic control
valve (20).
9.
Install two new O-rings (27) in hose assemblies (26)
and connect hose assemblies to main hydraulic control
valve (20).
427-C1108
10.
Install new O-ring (25) in hose assembly (24) and con-
nect hose assembly to main hydraulic control valve
(20).
11.
Install two new O-rings (23) in hose assemblies (22)
and connect hose assemblies to main hydraulic control
valve (20).
427-C1107
0218 00-11