• Home
  • Download PDF
  • Order CD-ROM
  • Order in Print
MAIN HYDRAULIC CONTROL VALVE INSTALLATION - CONTINUED
ELECTROHYDRAULIC CONTROL (JOYSTICK) REPLACEMENT

Field Maintenance Manual 2 For Loader, Heavy, Scoop: Diesel Engine Driven (Ded), 4-Wheel Drive 4.5 Cubic Yard Rock Bucket And 5.0 Cubic Yard General Purpose Bucket
Page Navigation
  1148    1149    1150    1151    1152  1153  1154    1155    1156    1157    1158  
img
.
TM 5-3805-291-23-2
MAIN HYDRAULIC CONTROL VALVE REPLACEMENT - CONTINUED
0218 00
MAIN HYDRAULIC CONTROL VALVE INSTALLATION - CONTINUED
20.
Fill hydraulic tank (WP 0148 00).
21.
Start machine (TM 5-3805-291-10) in order to raise
lift arms (1) and remove all tooling.
427-C0599
22.
Operate machine and verify correct operation of main hydraulic control valve (TM 5-3805-291-10).
23.
Shut down engine (TM 5-3805-291-10).
24.
Check for leaks.
END OF WORK PACKAGE