1. Position A/C receiver/dryer (Figure 1, Item 5) in clamp (Figure 1, Item 4).
2. Install two bolts and nuts (Figure 1, Item 1) on clamp (Figure 1, Item 4).
3. Lubricate two new O-rings (Figure 1, Item 3) with refrigerant oil and install in hoses (Figure 1, Item 2).
4. Connect two hoses (Figure 1, Item 2) to A/C receiver/dryer (Figure 1, Item 5).
END OF TASK
FOLLOW-ON TASKS
00092
1. Evacuate and recharge A/C system with refrigerant (WP 0093).
2. Install floor plate (TM 5-3805-292-10).
3. Install access cover (TM 5-3805-292-10).
4. Verify correct operation of machine (TM 5-3805-292-10).
END OF TASK