TM 5-2420-231-23-3
0270
INSTALLATION CONTINUED
WARNING
Use extreme caution when handling heavy parts. Provide adequate support and use
assistance during procedure. Failure to follow this warning may result in injury or death to
personnel.
NOTE
Cylinder weighs 75 lb (34 kg).
6. With assistance, position cylinder (Figure 3, Item 7) on machine.
7. Lightly grease and install pin (Figure 3, Item 6) and two retaining rings (Figure 3, Item 1) on machine.
8. Connect two hoses (Figure 3, Items 4 and 5) to fittings (Figure 3, Items 2 and 3).
Figure 3. Cylinder.
0270
END OF TASK
FOLLOW-ON TASKS
0270
2. Check hydraulic fluid level and fill as necessary (TM 5-2420-231-10).
3. Grease loader bucket cylinder (TM 5-2420-231-10).
END OF TASK
END OF WORK PACKAGE